Summer Facilities Projects
Summer Facilities Projects
Posted on 07/31/2020
This is the image for the news article titled Summer Facilities Projects

Orchard School Soil Remediation Project

The Orchard School soil remediation project began the week of July 13. At this time, all of the preliminary surveying has been completed, and the silt fencing has been installed. The contractor has been working around the building, the playground area, and the perimeter of the property. Earthmoving equipment and trucks have arrived, and the next phase of the project is expected to move quickly.
orchard


orchard group 2

Ridgewood High School Gym 3 Floor Remediation and Replacement Project

The remediation phase of the Gym 3 floor work is complete. The materials for the installation of the new flooring are expected to arrive in the first week of August, and the installation of the flooring should take approximately two weeks.
gym 3


Stevens Field Turf Replacement Project

The Stevens Field turf replacement project began with the removal and disposal of the turf. The new turf has been delivered, and the anticipated schedule of the project is as follows: 

 7/20-7/22: Install Netting Foundations

 7/23-7/25: Regrade Field and Inspect

 7/30: Turf Delivery and Layout

 7/31-8/3: Turf Sewing

 8/4-8/7: Turf Inlays

 8/10-8/13: Turf Infill

 8/14-8/17: Walkthrough/Punch List
stevens